Multi-Modal Sidewalk Project Phase Two Comes In Over Budget

Another bid, another over-budget price for Cookeville’s Spring Street sidewalk project, with hase two coming in $20,000 over projections. The city council rejected the first round of bids for phase two of the project. One of the two bids was over budget, and the other bid did not acknowledge an addendum. Community Development Director Jon […]
Cookeville Rebidding Spring Street Sidewalk Project

The Cookeville City Council moved to rebid phase two of the Spring Street Sidewalk Project on Thursday. In February, the city council rejected bids after the bids came in too high. Cookeville will now rebid the project with a contract adendum for the lump sum fee not to exceed $3,000.