Construction Officially Underway At Red Bud Village Site

Construction crews resuming work at Red Bud Village this week, despite frustrating delays.

Executive Director Chris Cassetty said Highlands Residential received funding through the Tennessee Housing Development Agency’s Tennessee Housing Trust Fund in September. The money closed enough of a financing gap to restart the project, although coordinating with the contractor and preparing subcontractors took longer than anticipated.

“It’s been kind of a little bit of a slow process and it’s been a little frustrating on my part,” Cassetty said. “But they had poured one of the footers Tuesday, they were digging the other footer yesterday.”

Cassetty said crews began digging the first footer last week despite unfavorable weather. Workers were installing rebar and leveling the ground as they prepared the second section of the foundation.

“When we were there yesterday, one footer had been dug and poured and it looked like they had probably another 40 or 50 feet of footer to dig on the other one,” Cassetty said.

Cassetty said he expected the contractor to pour the second footer Thursday, allowing crews to begin laying block. He said the work follows several months of preparation after the agency secured the additional financing.

Cassetty said he first noticed the construction activity while driving along Old Fly Valley Road and later returned to inspect the property with a staff member. He said the contractor now has workers and equipment on-site, marking the project’s transition from preparation to foundation construction.