Sparta finishing a three-year sewer improvement project designed to reduce stormwater infiltration, prevent pump clogs and upgrade aging infrastructure.
Sparta Public Works Director Dillard Quick said the $884,000 project included sewer line improvements and system upgrades.
“We also have a grinder pump that was installed,” Quick said, “When people flush these flushable wipes. It doesn’t say on the package that it’s good for grinder pumps. So it’s going to be better on our team to not have to go out and pull a pump because it’s clogged up.”
Quick said the improvements have also reduced some of the unwanted rainwater entering the sewer system, although the city has not determined the exact amount. The upgrades will primarily benefit employees responsible for monitoring pump stations and the sewer plant rather than produce noticeable changes in residential service.
Quick said obtaining equipment created one of the project’s biggest delays. One pump station took nine months to arrive as communities across the country competed for materials while spending American Rescue Plan Act funding.
“Everybody in the country was trying to get their money spent at the same time and the supply and demand was, we had more demand than we did supply,” Quick said. “So we’re not the only department that had issues as far as getting the materials that we needed to finish the project.”
Quick said crews also faced safety concerns while replacing sewer lines along active roadways, particularly when motorists approached flaggers and construction zones during their regular commutes.
Remaining work includes street restoration in areas where sewer replacements are complete but water line improvements are still underway. Quick said paving on Wall Street, Pearson Street, Polk Street and East Bronson will follow completion of the water line work.