Cookeville To Restore Aging Buck Mountain Water Tank

Design work set to begin on restoring Cookeville’s Buck Mountain water tank to address rust and metal deterioration caused by chlorine gas exposure.

Director of Water Quality Control Barry Turner said the steel structure was built in 1978 and has not been painted since 1992. Turner said the city council approved a $160,200 engineering contract to oversee the project. The design phase accounts for approximately $40,000 of that total.

“We inspect it at least once a year,” Turner said, “But we have a third party come in and inspect them every five years and do a thorough evaluation and you know sort of based on their recommendation it’s time to go ahead and paint it before we do start seeing metal loss.”

Turner said the project will require the two million gallon tank to be fully drained so crews can sandblast the interior.

“So you know that way you don’t have to replace some of the beams and stuff like that but on this job we’re actually looking about because of the cost to paint that dome on that tank, we’re looking about cutting the dome off and putting a aluminum geodesic dome on there where that’ll save us in future paint jobs because that’s there’s a lot of intricate work in painting inside that tank the structural beams and such,” Turner said.

Because the tank has a small opening, workers must bring scaffolding inside in pieces and assemble it within the structure.

“I think after everything’s done it’s about a week to before we can put water in it and then after we put water in it we’ll have to do a lot of testing, checking the water and the bacteria testing before we’d actually put it online,” Turner said.

Turner said the city expects the painting process to take between 120 and 150 days. Recent expansions at the water plant provide the city with the capacity to pump extra water and maintain service while the tank is out of operation.

“If it were to run on you know several more years, that’s why we’re need to get it painted now before it does start you know deteriorating the steel,” Turner said.

Turner said engineers will provide a more precise cost estimate for the repairs once the design work is finished.